Completed
Emergency building, Shirkhorshid Hospital, Abadan
- Steel weight
- 480 t
- Duration
- 50 days
Products & services
Building frames with plate-girder columns and beams, built with submerged-arc welding and pinned or moment connections, for office, sports and healthcare buildings.
In a welded frame, box columns or double I-section columns and I-shaped main beams are fabricated in the factory and joined on site by CO₂ and submerged-arc welding. This method suits buildings with an unusual layout or a short construction window.
Still undecided between a welded and a bolted frame? Read the article “Advantages of bolted steel frames” or talk to our technical office.
How we work
Reviewing architectural and structural drawings; calculating weight, schedule and cost.
Fabrication drawings for every member and connection, before any plate enters the shop.
Cold, hot and CNC cutting; girders and columns built with submerged-arc welding and checked to size.
Surface preparation and anti-corrosion coating for the hot, humid southern climate.
Every part coded and delivered on a schedule matched to erection progress.
Frame erection by our own crews, final inspection and handover to the client.
Built with this line
Completed
Completed
Completed
Completed